The arrival of Container Project Structure
Entering the smart container into the DIP branch to make an office with a size of 20 feet, length of 6 meters, and width of 3 meters

The first day of changing the container structure
Locating and cutting the place of doors and windows on the container and preparing for framing

Installation of Structures for Wall and Ceiling Panels
Execution of infrastructure and installation of structures for installation of roof panels and walls
Wiring and installation of Panels on the Wall
On this day, our experts performed all the project wiring according to the plan, then installed the false walls entirely in the project.
Stepped Ceiling Implementation
On this day, our skilled staff performed the final work of installing the false ceiling and the air conditioner stand.
Installation of doors, windows, air conditioners, and surface electricity
On this day, we installed aluminum doors and windows, as well as surface wiring, and the project air conditioner
Installing wallpaper inside the Container
On this day, our staff completely installed the interior wallpaper after the foundation, and then the electrical team installed the surface-mounted switches and sockets.
Parquet Installation
Before installing the parquet, spraying, foaming, and then installing the floor were done
The Outside View of the Container:
We considered stickers as the poster design for the exterior view. After preparing the surface of the container for sticker installation, our staff installed the sticker on the exterior part of the container. For the window part, we installed the transparent sticker with the ability to pass light.